NW Water Line Improvements
(South 19th Street)
The City of Bozeman’s rapid growth to the west and northwest of the city limits required that a major water system trunk line be installed along North 19th Avenue in anticipation of commercial and residential growth. Gaston Engineering & Surveying provided the surveying, planning, engineering and design, and construction management and inspection for this major water main along North 19th Avenue.
The project consisted of 18″ and 21″ diameter ductile iron water pipe, valves and fire hydrant assemblies. Another important aspect to this project was right-of-way acquisition along some areas of the new pipe alignment as well as connection to existing commercial services.
« Willow Creek Sewage Treatment ImprovementsFloodplain Study/Delineation (Baker Springs/Three Forks) »